Application Lodged | Lodged | 9/06/2020 | 9/06/2020 |
Allocate to Assessment Officer | Completed | 12/06/2020 | 12/06/2020 |
Which type of delegation is required? | RLPP Ryde Local Planning Panel | 11/12/2020 | 11/12/2020 |
Is notification required? | 21 days | 12/06/2020 | 12/06/2020 |
Referral sent to City Works & Infrastructure | Completed | 16/06/2020 | 16/06/2020 |
Referral sent to Development Engineer | Completed | 16/06/2020 | 16/06/2020 |
Referral sent to EHO | Completed | 16/06/2020 | 16/06/2020 |
Referral sent to Landscape Architect | Completed | 16/06/2020 | 16/06/2020 |
Letter drafted requesting additional information | Completed | 7/08/2020 | 7/08/2020 |
Referral sent to City Works & Infrastructure | Completed | 7/08/2020 | 7/08/2020 |
Referral sent to Development Engineer | Completed | 28/09/2020 | 28/09/2020 |
Referral sent to EHO | Completed | 28/09/2020 | 28/09/2020 |
Referral sent to City Works & Infrastructure | Completed | 28/09/2020 | 28/09/2020 |